Stages of Redevelopment Process

Stage 1

  • Offer Letter to the Society
  • Discuss and finalise terms and conditions with the Society
  • Concent letter from the society
  • MOU

Stage 2

  • Finalisation of Plan as per society requirements
  • DA/PA Agreement with the society
  • Approval of Plan from PMC
  • Once we receive Commencement Certificate from PMC start vacating the building.

Stage 3

  • Demolition of existing structure
  • Bhoomi Pujan
  • Apply for Rera Registration
  • Start construction of new building

Stage 4

  • Purchase TDR
  • Inward file in Corporation for Revise sanction
  • Obtain Completion certificate from PMC

Stage 5

  • Society formation
  • Conveyance deed

Documents Required From Society

  • 7-12 Extract
  • Search Report and Title Clearence
  • Index II
  • NA Order
  • Copy of Sanction Plan
  • Commencement Certificate
  • Building Completion Certificate
  • Society Registration Certificate
  • Conveyance Deed/Sale deed
  • List of Society members and their Flat Rera Carpet Areas
  • Share Certificate
  • Mutation Entries

Specifications

R.C.C

  1. Earthquake resistant framed structure conforming to ISS codes.
  2. Brickwork – ACC blocks.
  3. Plaster
    • External Walls – Double coat with special water Proofing treatment, using Reliance Fibers.
    • Internal – Neeru finish.
  4. Flooring & Tiling
    • Light Colored Vitrified tiles in all rooms.
    • Antiskid ceramic flooring in toilets and terraces.

Doors

  1. Decorative main entrance door.
  2. Main door with Safety lock, night latch, tower bolt & magic eye for entrance door.
  3. Granite / Marble frame for all washroom doors.

Windows

  1. Powder coated aluminum sliding windows with mosquito net.
  2. All windows with safety grill in mild steel.
  3. Granite / Marble window sill.

Kitchen

  1. Granite top kitchen platform with stainless steel sink.
  2. Glazed / ceramic tiles dado up to ceiling.
  3. Jaguar / Equivalent C.P. fittings.
  4. Provision for water purifier.
  5. Provision for exhaust Fan.

Washrooms

  1. Jaquar / Equivalent C. P. Fittings.
  2. Dado tiles up to ceiling.
  3. Concealed G. 1. Pipes plumbing with hot and cold arrangements.
  4. Provision for exhaust fan.
  5. Provision for water heater.

Electrifications

  1. Branded MCB and ELCB (Earth Leakage Circuit Breaker) for apartment
  2. Adequate points with branded modular switches (Anchor Roma/ Legrand)
  3. Copper wiring (Polycab / Finolex).
  4. TV points in living room and master bedroom.
  5. 15 Amp power points for washing machine, microwave, air conditioner refrigerator and water heater.
  6. Provision for internet point

Painting

  1. Water resistant paint for external walls.
  2. O.B.D. paint on internal walls.

Get In Touch

305, International Business Bay (IBB),
Guru Nanak Nagar, Opp Kumar Pacific
Mall, Near Swargate, Pune
Maharashtra 411042

Email: admin@shreeshalandmark.in

Vinod Danavale +91 9168355023

Sawan Chandak +91 9730812079

Get In Touch

© 2023 Shreesha Landmark Created with Ninad Web Tech

Get In Touch

301 & 302, International Business Bay(IBB), Guru Nanak Nagar,
Opp Kumar Pacific Mall,
Near Swargate, Pune
Maharashtra 411042

Email: sawanchandak@gmail.com

Vinod Danawale +91 9168355023

Sawan Chandak +91 9730812079

© 2023 Shreesha Landmark Created with Ninad Web Tech